COMPLETE SERVICE OF MV TRANSFORMER 132/3 25MVA Project Details
EDIT DETAILProject Information
Title: COMPLETE SERVICE OF MV TRANSFORMER 132/3 25MVA
Ref No: CPAX/2026/08/38
Creator: Jumanne Macha
Client: VEGA INTERNATIONAL
Project Type: commercial
Location: TWIGA CEMENT WAZO
Project Details
Budget: 19,000,000.00
Start Date: 2026-07-02
Expected Completion Date: 2026-08-14
Status: completed
Created Date: 2026-07-06
Last Updated: 2026-10-02 22:55:50
Budget Tracking
Total Costs: 17,450,000.00
Remaining: 1,550,000.00
Budget Used: 91.8%
Progress:
Budget Warning!
Involved Reimbursable Cost
| # | Date | Item Name | Amount |
|---|---|---|---|
| 1 | 08 Jul 2026 | Lockpad,safety Harness, safety | 950,000.00 |
| 2 | 08 Jul 2026 | Lockpad,safety Harness, safety | 700,000.00 |
| 3 | 10 Jul 2026 | Labour costs | 1,075,000.00 |
| 4 | 13 Jul 2026 | Labour costs | 350,000.00 |
| 5 | 14 Jul 2026 | Labour costs | 385,000.00 |
| 6 | 17 Jul 2026 | msasa | 140,000.00 |
| 7 | 17 Jul 2026 | Hydrox | 400,000.00 |
| 8 | 17 Jul 2026 | PPE gloves | 50,000.00 |
| 9 | 07 Jul 2026 | Technical kit & Operator Charg | 5,000,000.00 |
| 10 | 06 Aug 2026 | Technical kit & Operator Charg | 8,400,000.00 |
| Total Costs: | 17,450,000.00 | ||