Contruction of 33KV Transmission Line for Solar Project Project Details
EDIT DETAIL

Project Information

Title: Contruction of 33KV Transmission Line for Solar Project
Ref No: CPAX/2025/07/5
Creator: Admin Admin
Client: TWIGA cement
Project Type: industrial
Location: WAZO HILL-DAR ES SALAAM

Project Details

Budget: 49,950,000.00
Start Date: 2025-07-17
Expected Completion Date: 2025-08-30
Status: cancelled
Created Date: 2025-07-17
Last Updated: 2025-11-08 18:44:41

Budget Tracking

Total Costs: 12,449,000.00
Remaining: 37,501,000.00
Budget Used: 24.9%
Progress:
Involved Reimbursable Cost
# Date Item Name Amount
118 Jul 2025Labour costs865,000.00
221 Jul 2025protective Equipment250,000.00
321 Jul 2025Gatepass fees206,000.00
421 Jul 2025transport allowance30,000.00
521 Jul 2025transport allowance30,000.00
620 Jul 2025survey costs65,000.00
720 Jul 2025structure drawing fees300,000.00
823 Jul 2025PPE gloves60,000.00
924 Jul 2025sub-contractor payments500,000.00
1024 Jul 2025Material Purchases1,010,000.00
1127 Jul 2025Labour costs450,000.00
1227 Jul 2025protective Equipment550,000.00
1327 Jul 2025PPE gloves37,000.00
1431 Jul 2025PPE gloves39,000.00
1506 Aug 2025Food and water Expenses130,000.00
1631 Jul 2025Labour costs42,000.00
1730 Jul 2025Food and water Expenses35,000.00
1806 Aug 2025PPE gloves50,000.00
1907 Aug 2025Fuel Allowance33,000.00
2009 Aug 2025Labour costs850,000.00
2113 Aug 2025first Aid kit160,000.00
2216 Aug 2025Labour costs90,000.00
2316 Aug 2025Fuel Allowance40,000.00
2416 Aug 2025Labour costs95,000.00
2521 Sep 2025Labour costs100,000.00
2626 Aug 2025Labour costs505,000.00
2727 Aug 2025sub-contractor payments1,000,000.00
2825 Aug 2025Gatepass fees220,000.00
2919 Sep 2025sub-contractor payments500,000.00
3024 Sep 2025Food and water Expenses10,000.00
3124 Sep 2025Material Purchases215,000.00
3214 Oct 2025sub-contractor payments500,000.00
3315 Oct 2025Labour costs10,000.00
3415 Oct 2025Material Purchases210,000.00
3521 Oct 2025Material Purchases30,000.00
3626 Oct 2025Labour costs110,000.00
3725 Oct 2025Food and water Expenses38,000.00
3804 Oct 2025Labour costs300,000.00
3904 Oct 2025Food and water Expenses8,000.00
4008 Oct 2025PPE gloves40,000.00
4108 Oct 2025Food and water Expenses36,000.00
4205 Nov 2025sub-contractor payments2,700,000.00
Total Costs: 12,449,000.00